DOCUMENT CONTROL AND DESIGN CHANGES
REQUIREMENTS
Using the cross-reference to ISO 9001:1994, and ISO/DIS 13485
section 4.4.9 Design changes. We recommend than each manufacturer shall
establish and maintain procedures for the identification, documentation,
validation or where appropriate verification, review, and approval of
design changes before their implementation.
POINTS TO CONSIDER
There are two principal administrative elements involved in
controlling design changes: Document
control-enumeration of design documents, and tracking their status
and revision history. Throughout this section, the term "document"
is used in an inclusive sense to mean all design documents,
drawings, and other items of design input or output which
characterize the design or some aspect of it.
Change
control-enumeration of deficiencies and corrective actions arising
from verification and review of the design, and tracking their
resolution prior to design transfer.
For a small development project, an adequate process for
managing change involves little more than documenting the design change,
performing appropriate verification and validation, and keeping records
of reviews. The main objectives are ensuring that: corrective actions are
tracked to completion;
changes are implemented
in such a manner that the original problem is resolved and no new
problems are created; or if new problems are created, they are also
tracked to resolution; and
Design documentation is
updated to accurately reflect the revised design.
For projects involving more than two persons, coordination and
communication of design changes become vitally important. In other
words, manufacturers should take steps to avoid the common situation
where, for example, Jon and Marie agree to a make a change but neglect
to inform Pat of their decision. Manufacturers are usually quite comfortable with the processes
of document control and change control with respect to managing
manufacturing documents. The principles of these processes are reviewed
in the following paragraphs. Subsequently, we will explore how these may
be applied to design activities. DOCUMENT CONTROL.
The features of a manufacturing document control system
typically include the following:
Documents should be
identified (i.e., named and numbered) in accordance with some
logical scheme which links the documents to the product or component
they describe or depict and illuminates the drawing hierarchy.
A master list or index
of documents should be maintained which presents a comprehensive
overview of the documentation which collectively defines the product
and/or process.
Approval procedures
should be prescribed which govern entry of documents into the
document control system.
A history of document
revisions should be maintained.
Procedures for
distributing copies of controlled documents and tracking their
location should be prescribed.
Files of controlled
documents should be periodically inventoried to ensure that the
contents are up to date.
A person or persons
should be assigned specific responsibility to oversee and carry out
these procedures. It is desirable that the document control system
be administered by a person who is not directly involved with
developing or using the documents. For a small manufacturer,
document control might be a part-time job for a technician or
clerical staff person. More typically, one or more librarians or
full-time clerical or paraprofessional employees are required to
administer the system.
There should be a procedure for removal and deletion of obsolete documents.
CHANGE CONTROL.
Manufacturing change control is usually implemented using a set
of standardized procedures similar to the following: A change request might
be originated by a developer, manager, reviewer, marketing
representative, user, customer, quality assurance representative, or
production personnel, and identifies a design problem which the
requester believes should be corrected. Change requests are
typically reviewed following the manufacturer's prescribed review
process, and the request might be rejected, deferred, or accepted.
If a change request is
accepted and corrective action is straightforward, a change order
might be issued on the spot to implement the change. The change
order pertains to an explicitly identified document or group of
documents, and specifies the detailed revision of the document
content which will fix the identified problem.
Often, the change
request results in an assignment to developers to further study the
problem and develop a suitable corrective action. If the change is
extensive, wholesale revision of affected documents may be warranted
in lieu of issuing change orders.
Change requests and
change orders should be communicated to all persons whose work might
be impacted by the change.
It may not be practical
to immediately revise documents affected by a change order. Instead,
the common practice is to distribute and attach a copy of the change
order to each controlled copy of the original document.
Change control
procedures should incorporate review and assessment of the impact of
the design change on the design input requirements and intended
uses.
A mechanism should be
established to track all change requests and change orders to ensure
proper disposition.
Change control
procedures are usually administered by the document control staff.
APPLICATION OF DOCUMENT AND CHANGE CONTROLS TO DESIGN.
The design control system has to be concerned with the creation
and revision of documents, as well as the management of finished
documents. Additional mechanisms are required to provide needed
flexibility while preserving the integrity of design documentation.
These additional mechanisms are embodied in the procedures for review
and approval of various documents. It is important that the design change procedures always
include re-verifying and re-validating the design. Fortunately, most
design changes occur early in the design process, prior to extensive
design validation. Thus, for most design changes, a simple inspection is
all that is required. The later in the development cycle that the change
occurs, the more important the validation review becomes. There are
numerous cases when seemingly innocuous design changes made late in the
design phase or following release of the design to market have had
disastrous consequences. For example, a manufacturer encountered problems in the field
with a valve sticking in a ventilator due to moisture in the breathing
circuit. The problem was resolved by slightly increasing the weight of
the disc. Since the change was minor, minimal testing was performed to
verify the change. Subsequently, when the revised valves entered
production, significant numbers of valves began failing. Investigation
revealed that the heavier disc was causing the valve cage to separate
due to higher inertia. This failure mode was more serious than the
original sticking problem, and resulted in a safety recall. |
|
|
Tag Services: Los Angeles engineering, Mechanical engineer Los Angeles, Drafting Los Angeles, Mechanical engineering Los Angeles, SolidWorks ca, solidworks industrial design, Engineering companies Los Angeles, Industrial design Los Angeles, Product design Los Angeles, Consulting firms Orange County, Engineering firms in Los Angeles, solidworks training, Prototyping Los Angeles, Engineering companies in Orange County, Product development Los Angeles, 3d design Los Angeles, Drafting services Los Angeles, Industrial design Orange County, 3d cad modeling Los Angeles California, 3d cad design Los Angeles, solidworks cosmos. | ||